Felt

CONTRACT :- Dean Oaks Primary School - Wilmslow
MAIN CONTRACTOR :- Interserve Building
AREA :- 230m
VALUE :- 95K
SPECIFICATION :- Icopal profiles vapour vent x L
120mm Thermal P.I.R. insulation
Profiles vent x L
Firesmart profiles x L blue/grey

Working within schools environments can be a hard task. This contract was both refurbishment and new build.
Careful planning and programming for work undertaken during term time was of paramount importance.
Contract was completed successfully and on time by working closely with the main contractor.


CONTRACT :- C. P. School - Gadishead
MAIN CONTRACTOR :- G & J Seddon Ltd
AREA :- 410m
VALUE :- 41K
SPECIFICATION :- Strip off existing roof covering
S&L Bauder TA600 preparation layer
KSA - Duo torch-on underlay
K5K mineral cap sheet

A refurbishment contract with many on site restrictions. Careful planning of access for operatives and materials coupled with waste removal gave operatives a tough contract to complete. Works undertaken diligently and competently to bring contract in on-time.



Green Roofs

 

CONTRACT :- Sacred Heart School - Wigan
MAIN CONTRACTOR :- Robinson of Wigan Ltd
AREA :- 160m
VALUE :- 24K
SPECIFICATION :- Bauder DSI-Duo vapour control layer
120mm P.I.R. insulation
G4E torch-on underlay
Plant 'E' mineral cap sheet
2 layer PE foil
6mm Eco protection mat
DSE drainage board
Filter fleece
80mm Extensive substrate
Individual plug plants

A new build project completed in a busy school environment. Care had to be taken in the organisation of deliveries and movement of operatives. Contract produced a green roof which was aesthetically pleasing and will be tended to by the school pupils on a regular basis.


CONTRACT :- All Saints School - Bootle - Liverpool
MAIN CONTRACTOR :- Nobles Construction Ltd
AREA :- 2,260m
VALUE :- 285K
SPECIFICATION :- Bauder DSI-Duo vapour control layer
100mm P.I.R. insulation
G4E torch-on underlay
Plant 'E' mineral cap sheet
X F 301 Sedum layer & moisture mat

One of the largest school green roofs in England. With both flat and pitched roofs in its design, the green roof system had to be carefully laid. The installation of a 'leaky pipe' watering system was successfully incorporated within the roof build up.
Contract has produced a first class example of a large green roof.


Single Ply

 

CONTRACT :- John Lennon Airport Hotel - Liverpool
MAIN CONTRACTOR :- S.C.C. Ltd - Sheffield
AREA :- 890m
VALUE :- 98K
SPECIFICATION :- Sika Irocal S-vap 500E
90mm P.I.R. insulation
Irocal SGmA single ply membrane
SBV protection fleece
20-40 stone ballast

Single ply works completed on very busy main contractor site. A new build contract which had to be well planned, organised and undertaken speedily. Within the works many roof protrusions and abutments had to have 'bespoke' made details to adapt to roof that constantly changed during its installation.

 

CONTRACT :- Abito - Manchester
MAIN CONTRACTOR :- Barillion
AREA :- 1350m
VALUE :- 146K
SPECIFICATION :- High performance felt vapour control layer
But-to-falls insulation
Aluitra Evalon 'V' fleece backed single ply membrane

Another extremely busy new build site. Working up to 11 floors height gave operatives a challenging task in accessing materials. With each roof having its own 'Cut to Falls' system very careful planning and precise fixing led to paved terraces giving a pleasing finish enabling owners to enjoy the view of the Manchester skyline.

 

CONTRACT :- Council Offices - Sunbury St - St Helens
MAIN CONTRACTOR :-  
AREA :-  
VALUE :- 58K
SPECIFICATION :-  


CONTRACT :- Wallasey High School
MAIN CONTRACTOR :- Wirral School Services
AREA :- N/A
VALUE :- 170K
SPECIFICATION :- Remove existing barrel roof lights
S&F X tralite nanogel filled polycarbonate
Barrel vault roof lights

 

 


 